Project Scope
Placement of 0-500 kg Category Rock (651.382 tons)
Placement of 3-6 ton Category Rock (99.004 tons)
Placement of 70 ton Precast Concrete Blocks (2.329 No’s)
Contractor
Meditram-Sotramest JV
Main Employer
Alger Ministry of Transport
Country
Algeria
Year of Production
2002