Project Scope
Installation of 43-tonne cap beams on the piles of the approach bridge,
Installation of 110-tonne span beams (38 pieces) on the approach bridge cap beams,
Installation of 143-tonne fender systems on the import side of the main pier,
Placement of precast concrete blocks,
Offshore heavy lifting operations.
Contractor
Saipem & Afcons JV
Main Employer
Sohar Port Authority
Country
Oman
Year of Production
2010