Project Scope

Installation of collar blocks and precast concrete water intake heads.
Installation of HDPE water intake pipes, 10.000 m length and Ø2.500 mm outer diameter.
Installation of 5 concrete inlet structures.
Installation of chlorination line.
Dredging and filling works with TSHD.
Bedding and levelling works.

Contractor

TML Construction

Main Employer

Samsung C&T Corparation

Country

Cezayir

Year of Production

2017 – 2020